S-34.1, r. 1 - Regulation respecting petroleum exploration, production and storage in a body of water

Full text
84. As of the moment at which the cement has developed a gel strength and until the minimum compressive strength has been reached, the authorization holder must not carry out work that could compromise the integrity of the cement and the holder must comply with the Industry Recommended Practice, IRP: #25, Primary Cementing, published by the Drilling and Completions Committee.
O.C. 1251-2018, s. 84.
In force: 2018-09-20
84. As of the moment at which the cement has developed a gel strength and until the minimum compressive strength has been reached, the authorization holder must not carry out work that could compromise the integrity of the cement and the holder must comply with the Industry Recommended Practice, IRP: #25, Primary Cementing, published by the Drilling and Completions Committee.
O.C. 1251-2018, s. 84.